Bill of materials basics: levels, where-used and costing

Single-level vs multi-level BOMs, where-used lists, explosion and roll-up costing explained for small and mid-sized manufacturers.

A bill of materials (BOM) is the recipe for a product: every raw material, part and sub-assembly, in the quantity needed to make one unit. Almost every planning, purchasing and costing decision in a factory depends on it, so it pays to get the structure right.

Single-level and multi-level BOMs

A single-level BOM lists only the items that go directly into the finished product. A multi-level (indented) BOM also shows what goes into each sub-assembly, and what goes into those, down to purchased parts and raw material.

If you make sub-assemblies in-house, use a multi-level BOM. It lets you plan production of the sub-assembly separately, keep it in stock, and see the full material requirement for an order.

Explosion and "how many can I build"

Explosion multiplies the BOM by the order quantity to give the total requirement for every component. Comparing that requirement with stock on hand answers the question planners ask every day: how many can I build with what I have, and what is short?

Where-used

A where-used list works the other way round: pick a component and see every product that uses it, directly or through sub-assemblies. It is essential when a supplier changes a part, a price rises or a component is discontinued.

Revisions and effectivity

Products change. An engineering change note (ECN) records what changed and why, and date effectivity controls from which date the new version of the BOM is used. Without it, planners and stores end up working from different versions.

Roll-up costing

When each component has a cost and each operation a rate, the BOM can be "rolled up" to give the material and conversion cost of the finished product. Rolling up again after a price change shows its effect on margin immediately, which is far more reliable than updating a costing spreadsheet by hand.

Common BOM mistakes

  • Units that do not match: buying in kilograms, issuing in grams, with no conversion defined.
  • Scrap and process loss left out, so material always runs short.
  • Phantom or "free issue" items mixed with purchased items.
  • One BOM per customer variant instead of options on a common structure.

See how BOMs work in Dimexa ERP on the Bill of Materials page, or book a free demo with one of your own product structures.

Back to all articles

See Dimexa ERP with your own process

Book a free, no-obligation walkthrough. Tell us how you work today and we will show you the matching screens in Dimexa ERP.

Chat on WhatsApp